Updated on 22 November 2026 : a new drilling campaign is under way east of Neuchâtel station, near the entrance of the future tunnel under the Chaumont hill. These surveys are to help choose the excavation techniques and the dimensions of the trenches and tunnels, according to ArcInfo.
Background
The current railway line between Neuchâtel and La Chaux-de-Fonds forces trains to reverse at Chambrelin. A new direct line is to eliminate this manoeuvre. The project is led by the Federal Office of Transport (FOT), SBB and the canton of Neuchâtel, and includes two tunnels.
The key points
The preliminary design of the direct Neuchâtel–La Chaux-de-Fonds railway line is complete, the FOT, SBB and the canton of Neuchâtel announced on Thursday 19 November 2026. The final route is now known.
The project cost amounts to CHF 1.4 billion, including connection works. The schedule will take into account the decision to build the two tunnels one after the other, and the budget will be refined. In Val-de-Ruz, the open-air section will be reduced from 1.4 to around 1.2 kilometres to limit the footprint on the territory.
Key figures
- CHF 1.4 billion : project cost, including connections
- Around 1.2 km : length of the open-air section in Val-de-Ruz, compared with 1.4 km previously
- 2 tunnels : built one after the other
What it means for businesses
- Companies in the Neuchâtel mountains and lakeside : removing the Chambrelin reversal will improve the rail link between the canton's two hubs.
- Civil engineering companies : the project enters a detailed planning phase, with adjustments to reduce site footprints and disruption.
Further reading
Sources
- RFJ (ATS) – Neuchâtel-La Chaux-de-Fonds direct line: final route known
- watson – Neuchâtel-La Chaux-de-Fonds: SBB unveils the route
- ArcInfo – Drilling at Neuchâtel station for the direct line