The canton of Geneva lacks ice surfaces for hockey, figure skating and recreational sport. To meet this need, the State has been preparing new ice rinks at the Trèfle-Blanc site in Lancy for several years. An architectural competition was presented in 2024, and the Grand Council voted the investment credit in 2025. One appeal was still holding up the building permit.
The key points
The Department of Social Cohesion (DCS) and the Department of Territory (DT) announced on 9 November 2026 the start of construction. The only appeal against the building permit has been withdrawn, so the permit is now in force. The project thus moves into its delivery phase.
Preparatory works begin on 16 November 2026. Earthworks will follow in the first quarter of 2027, according to the Canton's provisional schedule. Delivery is planned for summer 2032 at the earliest. According to Léman Bleu, this deadline has already been pushed back twice.
The project includes two ice rinks, an underground park-and-ride car park and new public spaces. The main arena will host the Genève-Servette ice hockey club, according to Léman Bleu.
Key figures
- CHF 275.5 million : investment credit voted by the Grand Council for the site and outdoor areas (Léman Bleu)
- 8,500 seats : capacity of the main arena
- 2 ice rinks planned on the site
- Summer 2032 : earliest delivery
What it means for businesses
- Construction : a multi-year building site opens in Lancy, with earthworks from 2027
- Lancy residents and shops : the Canton promises new public spaces and redesigned mobility in the Trèfle-Blanc area
Who says what
- Thierry Apothéloz (State Councillor in charge of the DCS): the building permit taking effect marks a “decisive step” and shows the support the project enjoys
What's next
- Preparatory works begin on 16 November 2026
- Earthworks in the first quarter of 2027
- Opening at the earliest insummer 2032